Closure and reclamation support for a legacy metals mine

About this project

client
Teck Metals, Ltd.
location
Northwest Territories
completion date
Ongoing

The Pine Point lead-zinc mine, which operated from 1964 to 1988, included more than 50 open pits and associated waste-rock dumps, a mill site and concentrate loadout, a tailings impoundment area containing processing waste, and associated infrastructure. The pits, mill site, roads, waste-rock dumps, and powerlines were reclaimed to the standards in place at the time the mine closed, and the land leases were returned to the government. Teck Metals retained the lease for the tailings impoundment area to supply ongoing care and maintenance.

In 2017, the Mackenzie Valley Land and Water Board asked Teck to submit an updated closure and reclamation plan for the tailings area that followed revised guidelines the board had issued in 2013. The newer guidance was based on the closure principles of physical and chemical stability, no need for long-term active care, and compatibility with future land use. 

Before a revised closure plan could be developed, more information about the site was needed to provide a better understanding of the fate and transport of zinc and other metals within the tailings area. Barr developed a multi-year research plan to study metal concentrations as well as the fate and transport of metals across the site. We also studied the watersheds and surface-water routing, groundwater conditions, and the water balance and geochemistry at the site, and conducted an assessment of human-health and ecological risks associated with the existing conditions. In 2018, the Mackenzie Valley Land and Water Board authorized the research plan for implementation.

Barr’s work began with reviewing the existing closure plan for the tailings area, which covers 2 square kilometers and contains 54 million tonnes of tailings from the mine. From there we identified the research activities and studies needed to resolve remaining uncertainties and data gaps, and developed a phased approach for implementing that work. The results of the research and studies is helping Teck choose the best overall closure option and further revise its long-term plan.

One field component of the research involved collecting environmental samples to obtain a better understanding of the tailings’ chemical and physical characteristics. Geochemical testing — aimed at investigating the potential for ongoing metals leaching due to the weathering of sphalerite and other trace minerals — included static testing, column leaching, and evaporative drying tests.

Data from the samples were incorporated into several desktop studies. Using the GoldSim platform, Barr developed coupled water-balance and fate-and-transport models that incorporated methods for evaluating closure options offering climate-change resiliency. That integrated modeling was key to informing development of the closure and reclamation plan. Other supporting studies are currently underway.

Engaging local Indigenous communities allowed Teck and Barr to learn what the communities envisioned for the restored site, including how it should look and what it should provide. Involving local communities early in the research process helped shape studies to address their concerns. For example, concerns related to the potential for dust generation have arisen in meetings and Barr has performed air dispersion modeling to assess potential risks and inform future decision making. In addition, we partnered with community members to collect samples of surface water and wild berries.

Barr prepared the research plan and revised the larger closure plan with the outcome in mind: long-term closure that is cost-effective, meets regulatory requirements, and addresses community concerns. Addressing high-level tasks up front and conducting work in phases has kept activities focused on the key issues, so that time and money aren’t taken up by noncritical pursuits.

Barr has also been supporting annual water-treatment operations at the site, including forecasting pondwater levels and the timing of spring melt so operators can schedule resources; evaluating the efficacy of the lime low-density-sludge process; and assisting with process optimization plans. In addition, we have bench- and field-tested several chemical aids to improve particle formation and settling.

Key team members

Cory Anderson

Senior Water Resources Engineer

Joelyn Kozar

Senior Wetland Ecologist

Dale Kolstad

Vice President
Senior Environmental Engineer

Todd Fasking

Vice President
Senior Environmental Consultant

Marc Mills

Environmental Specialist

Related closure and reclamation projects

Stationary-source evaluation for asphalt plants
Pre-acquisition environmental due diligence review
Phase I ESA for copper-nickel project
Siting and permitting for saltwater disposal wells
Ore transportation study
Detailed assessment of phosphorus sources and loading to Minnesota watersheds
Dry-stack tailings management
Permitting, environmental assessment, and design for copper-nickel mine
Tailings basin expansion and closure options
Routine electrical, controls, and instrumentation support
Preliminary engineering for Mouse River enhanced flood protection project
Geotechnical investigation and design for expansion of ancient gold mine
Electric-energy resource options study
Environmental impact assessment for mountain-bike trail
Scoping study to increase magnetite-concentrate production capacity
Development of sewer plan and update of model
Upper Sheyenne River erosion and sedimentation risk assessment
Mine closure and reclamation
Water supply sustainability study for City of Rochester
Capture-efficiency testing for ethanol production facility
Study of engineering risks and site feasibility for windpower client
Chemical and biological monitoring of test ponds
Natural resources inventory and stewardship recommendations
Water-quality modeling and mapping for watershed district
Landslide stabilization design for an underground coal mine
Infiltration updates to the Minnesota Stormwater Manual
Geologic modeling and mine-plan development for aggregate quarries
Resource estimates for neodymium-rich rare-earth-element exploration project
Rapid response planning for aquatic invasive species
Environmental review for proposed natural-gas pipeline
Waste-gas scrubber design engineering for taconite pellet plant
Assessment and remediation of former dump site on university campus
Sustainable landscape master plan for Minnesota college campus
Updating of Lake Superior chemical source inventory
Upgrade of wastewater treatment system
Upgrades and expansion for silica-sand wet plant
Reclamation of legacy tailings site
Environmental liability assessment at manufacturing facility
Engineering services for frac-sand operation
Environmental review and prefeasibility design for planned uranium mine
Vulnerability assessment of municipal stormwater system
Vulnerability assessment of a city’s aging storm sewer system
Test burn for cofiring coal and biomass
Transmission line EIS
Living-streets planning provides framework for alternative street reconstruction
West Side Flats park and stormwater design
District stormwater management system for redeveloping urban center
Non-segregating tailings deposition study
Modeling and failure risk assessment of a municipal storm sewer system
Highwall stability assessment
XP-SWMM model update and calibration for Minnesota watershed
Mine remediation and reclamation
Air permit-to-install strategy and application
Hiawatha Golf Course alternatives analysis and master planning
Identification of wetland restoration opportunities
Watershed management planning for Minnesota watershed district
Site reviews for solar gardens across Minnesota
Removing dissolved metals from roadway runoff using ferric-oxide filtration
Geotechnical deformation and failure modeling of fine tailings capping
Stormwater-management minimal impact design standards and BMP design calculator
Hydropower facility evaluation and due diligence
Public-space and sustainable stormwater management decision-making framework
Tailings-management area design and construction
Spillway design for iron-ore-mining and mineral-processing facility
Stormwater-development reviews for urban WMO
Reclaimed mineland offers worldclass mountain biking and economic development
Environmental site assessments for future site of mining and processing facility
Condition assessment and options study for hydro facility
One Watershed, One Plan development for southern Minnesota watershed district
EIS preparation and third-party environmental review of transmission line
Resource assessment and permitting assistance for industrial sands facility
Engineering services for industrial chemicals mine and processing facility
Trona-mining production optimization
Groundwater-flow model of the Twin Cities metro area
Geotechnical assistance for mine expansion at Julienne Lake
Development of a citywide GIS-based stormwater management water-quality model
Shoreline stabilization and restoration of Lake Minnetonka’s Big Island
Landscape master plan for Minnesota college campus
Stormwater infrastructure management assistance
Compliance, resource, and process evaluations for potential mining sites
Dispersion modeling at five ethanol production facilities
Evaluating tunnel system pressure
Urban watershed stormwater-development and permit reviews
Ecological residential development design preserves nature and city growth
Redevelopment services for New Brighton Exchange
Energy integration study for waste-heat utilization
Strategic planning for Freeway Landfill
Environmental services for coal-yard decommissioning
Brownfields redevelopment for Mississippi WMO headquarters
Tongue River assessment
Environmental permitting and compliance support for a refinery
AFFF containment upgrades evaluation
Water reuse evaluation for zero liquid discharge at manufacturing facility
Redevelopment of former Atlas Cement plant
Expansion-related permitting and review assistance
Installation design for alternative energy facility
Aquifer storage and recovery and water sustainability evaluation and implementation
Preclassification system feasibility study, design, and construction support
Study of solar developments on closed Minnesota landfills
Geotechnical investigation of pumped-storage hydroelectric facility
Preliminary geotechnical engineering and geophysical investigation
Geotechnical highwall assessment at Bald Mountain
Seneca solar project geotechnical engineering services
Conceptual development for Coal FIRST initiative
Pre-FEED study for Coal FIRST initiative
Environmental services for cathodic protection facilities in Michigan
Transaction due diligence for oil and gas assets
Creating ESG clarity for a petroleum company
Above-ground tailings management and mine backfill
ESG policy review and advisory services
ESG framework for midstream oil and gas company
Mitigation of aerosol impacts from coal combustion
Hydropower facility evaluation and improvement recommendations
Analysis of microbial ecology in selenium bioreactor
Statistical analysis of coal-silo vibrations
Business risk assessment of species at risk in oil sands region
Upgrades to mineral processing plant
Aggregate resource estimate along proposed pipeline routes
Field review and permitting for pipeline replacement
Environmental field review and MPSC Act 9 support
Solar on reclaimed coal mine, settlement and subsidence risk analysis
Pressure control valve methanol-injection engineering study
UAS topographic data collection for habitat restoration design
City of Minnetonka natural resources management plan
Spring Lake Park Reserve natural resources management plan
Metropolitan Council sustainable landscape guidelines
Tailings dam safety inventory and semiquantitative risk analysis
Sustainable landscape master plan for Abbott Northwestern Hospital
Carbon-evaluation services for new mining facilities
Engineering services for solution mine
Assessment of PFAS use
Air permitting assistance for pharmaceutical facility
Process and plant design for potash mine
NEPA support for coal mine expansion
Redesign and optimization of crystallizer piping
Environmental support for solar power facilities
Desktop study and geotechnical investigation for new wind power site
Great lakes coastal wetland restoration feasibility study
Highland Bridge (Ford Site) green stormwater infrastructure
Bloomington natural resources prioritization and management
Natural resources management plan for recreational area
Pipeline route permitting assistance
Climate adaptation and resiliency plan
Renewable energy development plan
Carbon-capture-system feasibility study
Water discharge permitting for copper-nickel mine
Third-party dam safety review of tailings-storage facility
Tailings facility dam safety review
Combined hydrologic, hydraulic and water quality model for watershed planning
Detailed 1D/2D and 2D HECRAS modeling for watershed management